BP Business Economic Loss Claim Appeal 2017-773:Progran Accountant Properly Reallocated Construction Claimant’s Direct Job Costs and Owner/Officer/Employee Expenses

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-772: Professional Judgment of the Program Duly Exercised; Reallocation “Sufficiently Matched” Under Construction Methodology

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-768: SP Properly Adjusted Financials and Correctly Applied BEL, Not Construction, Methodology

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-705: Claimant Correctly Classified As “Construction” Instead of Real Estate Developer

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-627: Construction Methodology Correctly Applied to Mechanical Contractor Despite BP’s “Flexible” Argument

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-552: Construction Methodology Appropriate For Matching Profit and Loss Statements of Installer and Seller of Sound Equipment

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-342: AVM More Appropriate Than Construction Methodology For General Contractor In This Appeal

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-249:Construction Methodology and NAICS Code Improperly Applied To Real Estate Brokerage and Home Inspection Company

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-245:Construction Methodology Sufficiently Matches Construction Company’s P&L’s

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]

Tom Young

BP Business Economic Loss Claim Appeal 2017-196: AVM Applied Over Construction Methodology Despite Construction NAICS Code

The following is an Appeal Panel Decision issued pursuant to Section 6 of the BP Deepwater Horizon Economic & Property Damages Settlement Agreement and the Rules Governing the BP Appeals Process. Links may have been added to assist the reader. The original decision […]